The Westbrook School expansion project will follow a comprehensive, phased approach to ensure thoughtful planning and execution. Below is an overview of the key phases, milestones, and anticipated completion dates for this exciting project:
- Winter 2025: The first phase of the project focuses on conceptualizing the design. During this stage, the team develops initial concepts, explores design options, and begins shaping the vision for the expanded Westbrook School.
- Spring 2025: In this phase, the design is refined and finalized through collaboration with stakeholders and the district team. Structural systems, building systems, and material plans are developed, and the project undergoes code compliance reviews to ensure every detail meets regulatory standards.
- Summer 2025: This final planning phase involves creating detailed construction drawings and specifications. It is a meticulous process with multiple checkpoints to ensure accuracy and alignment. During this stage, architects and district leaders finalize plans and costs, culminating in comprehensive documentation of the entire design.
- September-October 2025: Bid process and Board approvals.
- Spring/Summer 2026 - August 2027: Once approved, construction begins in Spring/Summer 2026, with substantial completion anticipated by August 2027.